Stalled Lagun Perdana Project to be Completed by February Next Year

The long wait by owners of the stalled Lagun Perdana Apartments project will be over by February next year, according to Subang Jaya ADUN Hannah Yeoh.

 

Work to complete Block 1 & 8 has started and is expected to be completed by December this year while work on Block 3 is expected to be completed by February next year, according to Hannah.

 

However, the completion of Block 7 is delayed due to problems with the structure, which was found to be unsafe when IJM, the principal contractor for the revived project started work.

 

Together with the Housing and Local Government Ministry, the developer and contractors are working closely with the Lagun Perdana Owners Association to resolve the issues with the delay.

 

"The uncompleted work affects 1,411 owners. So many owners are without their homes for such a long time."

 

"Efforts to complete the project must not however compromise on safety," she said to reporters after making a brief visit to the site yesterday morning.

 

Hannah expressed her confidence with IJM, whom she considered as a reliable company entrusted to complete the project.

 

Block 1 has 354 units; Block 3 339 units; Block 7 359 units and Block 8 354 units altogether.

 

An official from the Ministry said they would monitor the progress of the construction and ensure that it was completed.

 


 

Want to be in the know? Sign up for email updates!
Note: Due to technical issues, we are no longer using the old email update list. To stay updated, you will need to sign up again. Please sign up here if you have not signed up before 22 July 2011.
Click here to unsubscribe from our email updates

Download SJ Echo

February 2012

Important Numbers

Advertisement

THIS MONTH'S ISSUE: FEBRUARY 2012

Monday, 6 February 2012

Special Community Feted at Joy of Combined Fest

» Read more

Tuesday, 3 January 2012

Download SJ Echo Apps

Community News at Your Fingertips

» Read more

Friday, 3 February 2012

Illegal Structure in USJ6 to be Removed

» Read more

Wednesday, 1 February 2012

Operating Illegally

Budget hotels mushrooming in Subang Jaya and operating without license

» Read more

Monday, 30 January 2012

SJ Echo Feb 1 2012 Edition

» Read more

Thursday, 2 February 2012

Sime Darby Healthcare expands to Ara Damansara

» Read more

Wednesday, 1 February 2012

Putting Our Best Foot Forward

» Read more

Wednesday, 1 February 2012

Time to restore the 4th Vote

» Read more

Wednesday, 1 February 2012

Gong Xi Gong Xi!

» Read more

Wednesday, 1 February 2012

Making Our Responsibility Count

» Read more

Wednesday, 1 February 2012

IT'S TIME FOR SUBANG JAYANS TO MAKE SOME NOISE

» Read more

Wednesday, 1 February 2012

GONG XI FA CAI!

» Read more

Wednesday, 1 February 2012

The Importance of DIABETES EDUCATION

» Read more

Wednesday, 1 February 2012

Celebration of Love

» Read more

Wednesday, 1 February 2012

Residents with a Mission

» Read more

Wednesday, 1 February 2012

Extended One More Month

» Read more

Thursday, 2 February 2012

Hello, My name is Ashleigh

» Read more

Friday, 3 February 2012

RAIDED: Three Online Gambling Dens in USJ21

» Read more


How Do I Advertise | Links | Downloads | Terms of Use